Surface Preparation :
Surface should be clean, dust free, oil free and dry.
Application :
IZOKAP should be applied to the entire substrate with a brush, roller or spray. If the application will be done more than one coat, 12 hours of waiting time is required.
Dosage :
1-1,5 kg/m2 for each layer, in case of layering layers should be applied perpendicular, drying time is 24 hours.
Storage :
Shelf life of IZOKAP is 2 years from the production date in dry and moisture free frost free ambient. Package should be kept tightly closed when not in use.
Package :
4 kg plastic pails, 20 kg of Tin